CAMPUS | PROJECT | BUDGET | SALE | STATUS |
Anderson Mill Elementary | Interior renovations (restrooms & office) | $168,750 | 4 | Complete |
Anderson Mill Elementary | Replace fire alarm system/security/alarms/access | $168,750 | 2,3 | Complete |
Berkman Elementary | Improve security at MDF room | $9,600 | 1 | Complete |
Berkman Elementary | Add card readers at two exterior doors | $27,500 | 1 | Complete |
Bluebonnet Elementary | Add parking area | $96,000 | 1 | Complete |
Brushy Creek Elementary | Electrical upgrades (lighting & circuits) | $52,000 | 1 | Complete |
Brushy Creek Elementary | Replace HVAC system at second floor | $312,000 | 4 | Complete |
Brushy Creek Elementary | Replace gym floor | $34,500 | 2 | Complete |
Brushy Creek Elementary | Electrical upgrades (kitchen circuits) | $39,000 | 3,4 | Complete |
Brushy Creek Elementary | Remodel restrooms/hand lavatory by exit doors | $198,000 | 4 | Complete |
Brushy Creek Elementary | Replace 400 wing classroom carpet | $33,462 | 4 | Complete |
Brushy Creek Elementary | Remodel kitchen area (equipment) | $185,443 | 4 | Complete |
Caldwell Heights Elementary | Replace flashing at 2nd Floor North Wing | $18,900 | 1 | Complete |
Callison Elementary | New Elementary School at Turtle Creek | $19,377,750 | 1,2 | Complete |
Canyon Creek Elementary | Replace existing fire doors | $120,000 | 3 | Complete |
Canyon Creek Elementary | Replace portion of EFIS at 2 story bldg exterior | $180,000 | 1 | Complete |
Caraway Elementary | HVAC projects | $355,550 | 1 | Complete |
Caraway Elementary | Replace hallway VCT | $48,000 | 4 | Complete |
Caraway Elementary | Replace existing fire alarm system | $101,250 | 4 | Complete |
Caraway Elementary | Demo the little red house (CANCELLED) | $60,000 | 1 | Complete |
Deep Wood Elementary | Restroom/handwashing area renovation | $26,000 | 1 | Complete |
Deep Wood Elementary | Site renovations (retain wall & sidewalks) | $130,000 | 4 | Complete |
Deep Wood Elementary | Improve site drainage | $120,000 | 3,4 | Complete |
Deep Wood Elementary | Electrical upgrades (lighting & circuits) | $165,800 | 3,4 | Complete |
Deep Wood Elementary | Replace roof system | $165,000 | 4 | Complete |
Double File Trail Elementary | HVAC retrofit projects (MAU’s & Thru Wall Units) | $1,113,750 | 4 | Complete |
Double File Trail Elementary | Replace existing PA, clock and bell system | $78,000 | 1,2 | Complete |
Double File Trail Elementary | Interior (restrooms & ceilings) | $264,000 | 4 | Complete |
Double File Trail Elementary | Replace classroom carpeting | $240,000 | 1 | Complete |
Fern Bluff Elementary | Replace gym floor | $34,500 | 2 | Complete |
Fern Bluff Elementary | Install emergency/exit light system | $7,500 | 1 | Complete |
Forest Creek Elementary | Replace kitchen HVAC unit | $39,000 | 1 | Complete |
Forest North Elementary | Remodel boy’s and girl’s restroom facilities | $117,000 | 4 | Complete |
Forest North Elementary | Add ventilation to the kiln room | $12,000 | 1 | Complete |
Gattis Elementary | Replace gym floor | $34,500 | 1 | Complete |
Gattis Elementary | Replace hall carpet w/VCT & all classroom carpet | $221,000 | 2 | Complete |
Gattis Elementary | Replace water heater/add sink to PPCD room | $23,400 | 2 | Complete |
Gattis Elementary | Seal all exterior masonry walls | $42,000 | 1 | Complete |
Gattis Elementary | Replace roofing system | $90,000 | 3 | Complete |
Great Oaks Elementary | Electrical upgrades (library & emergency lights) | $38,750 | 3 | Complete |
Jollyville Elementary | Site renovations (site drainage) | $275,000 | 4 | Complete |
Laurel Mountain Elementary | Site renovation (level playfield) | $108,000 | 2,3 | Complete |
Laurel Mountain Elementary | Site renovation (widen sidewalk) | $24,000 | 1 | Complete |
Live Oak Elementary | Replace hallway flooring | $39,000 | 3 | Complete |
Live Oak Elementary | Increase number of classroom for Deaf Ed (CANCELLED) | $4,400 | 1 | Complete |
Live Oak Elementary | Replace gym flooring | $34,500 | 2 | Complete |
Old Town Elementary | Electrical upgrades (lighting & distribution) | $151,200 | 2,3 | Complete |
Old Town Elementary | Replace existing PA, clock, and bell system | $78,000 | 1 | Complete |
Old Town Elementary | HVAC projects (split systems & make up air) | $585,000 | 3 | Complete |
Old Town Elementary | Replace gym floor | $34,500 | 1 | Complete |
Old Town Elementary | Replace roofing system | $120,000 | 4 | Complete |
Old Town Elementary | Replace all carpet at hallways with VCT | $300,000 | 3 | Complete |
Purple Sage Elementary | Reroof existing system | $360,000 | 1 | Complete |
Purple Sage Elementary | Interior renovations (ceiling, door locks) | $263,250 | 4 | Complete |
Purple Sage Elementary | Electrical upgrades (lighting & circuits) | $39,000 | 4 | Complete |
Purple Sage Elementary | Replace existing PA, clock and bell systems | $72,000 | 2,3 | Complete |
Purple Sage Elementary | Replace building carpet/cove base | $162,500 | 4 | Complete |
Purple Sage Elementary | Expand front sidewalk and drive | $48,000 | 4 | Complete |
Robertson Elementary | Electrical ungrades (switchboard & lighting) | $119,600 | 2,4 | Complete |
Robertson Elementary | Interior (restrooms & cabinets) | $170,300 | 4 | Complete |
Robertson Elementary | Replace asphalt front parking area | $159,480 | 3 | Complete |
Robertson Elementary | Replace carpet/renovate toilets at portables | $130,000 | 4 | Complete |
Robertson Elementary | Add fence around playground equipment | $13,750 | 1 | Complete |
Robertson Elementary | Replace existing playground equipment | $55,000 | 3 | Complete |
Sommer Elementary | New Elementary School at Avery Ranch | $17,634,000 | 1,2 | Complete |
Spicewood Elementary | Flooring projects (carpet and VCT replacement) | $174,000 | 1 | Complete |
Spicewood Elementary | Interior renovations (hand wash areas) | $26,000 | 1 | Complete |
Teravista Elementary | New Elementary School at Teravista (A/E Fees Only) | $1,066,287 | 1 | Complete |
Teravista Elementary | New Elementary School at Teravista (Construction Only) | $18,340,133 | 1 | Complete |
Teravista Elementary | New Elementary School at Teravista (FF&E Only) | $1,919,316 | 2 | Complete |
Voigt Elementary | Exterior plumbing projects (utility lines) | $330,000 | 3,4 | Complete |
Voigt Elementary | HVAC projects (kitchen make-up fan) | $9,750 | 3 | Complete |
Voigt Elementary | Replace gym floor | $34,500 | 1 | Complete |
Voigt Elementary | Carpet/tile replacement in classrooms/offices | $324,000 | 4 | Complete |
Voigt Elementary | Repair outdoor hard surface play area | $16,500 | 1 | Complete |
Voigt Elementary | MDF room renovations | $24,000 | 1 | Complete |
Voigt Elementary | Add keyless entry points | $3,600 | 1 | Complete |
Voigt Elementary | Parking lot repairs/additions | $64,800 | 3 | Complete |
Voigt Elementary | Electrical projects (lighting replacement) | $69,600 | 1,2 | Complete |
Voigt Elementary | Remodel kitchen area and replace equipment | $279,900 | 2,4 | Complete |
Wells Branch Elementary | Upgrade emergency lighting system | $16,800 | 1 | Complete |
Wells Branch Elementary | HVAC projects | $1,033,500 | 4 | Complete |
$69,261,821 |
CAMPUS | PROJECT | BUDGET | SALE | STATUS |
C.D. Fulkes Middle School | Add elevator to second floor (400 building) | $168,000 | 4 | Complete |
C.D. Fulkes Middle School | Electrical upgrades | $240,000 | 3,4 | Complete |
C.D. Fulkes Middle School | Install security cameras | $180,000 | 4 | Complete |
C.D. Fulkes Middle School | Replace wooden bleachers/press box at football field | $42,000 | 3 | Complete |
C.D. Fulkes Middle School | Remodel kitchen area | $235,375 | 1 | Complete |
Canyon Vista Middle School | Repurpose lecture room to gain classrooms | $590,000 | 2,4 | Complete |
Cedar Valley Middle School | Install redundant chiller/CW capacity | $500,500 | 3,4 | Complete |
Cedar Valley Middle School | Replace existing PA, clock and bell systems | $81,000 | 3 | Complete |
Cedar Valley Middle School | Replace main gymnasium floor | $132,250 | 2,4 | Complete |
Cedar Valley Middle School | Install security cameras | $180,000 | 2,3 | Complete |
Cedar Valley Middle School | Add HVAC system at industrial tech shop | $118,015 | 4 | Complete |
Chisholm Trail Middle School | HVAC projects | $304,850 | 2,4 | Complete |
Chisholm Trail Middle School | Install security cameras | $180,000 | 2,3 | Complete |
Chisholm Trail Middle School | Improve campus and football field drainage | $312,000 | 4 | Complete |
Chisholm Trail Middle School | Plumbing projects | $195,000 | 4 | Complete |
Chisholm Trail Middle School | Convert science rooms 306/310 into science labs | $143,000 | 4 | Complete |
Chisholm Trail Middle School | Interior renovation (nurse’s office/ADA restroom) | $96,330 | 4 | Complete |
Chisholm Trail Middle School | Interior renovations (exterior doors replacement) | $46,200 | 4 | Complete |
Chisholm Trail Middle School | Interior renovations (gym ceiling/lights) | $91,000 | 4 | Complete |
Deerpark Middle School | HVAC projects | $875,876 | 1 | Complete |
Deerpark Middle School | Install security cameras | $180,000 | 4 | Complete |
Deerpark Middle School | Install gates at rear drive | $24,000 | 1 | Complete |
Deerpark Middle School | Plumbing projects (replace boilers) | $234,000 | 1,4 | Complete |
Deerpark Middle School | Electrical upgrades (lighting & circuits) | $279,500 | 4 | Complete |
Deerpark Middle School | Repurpose 6 classrooms to science classrooms | $312,000 | 4 | Complete |
Deerpark Middle School | Recarpet all classrooms/administration area | $220,000 | 4 | Complete |
Deerpark Middle School | Construct wall at tech ed shop/classroom CANCELLED | $135,600 | 3 | Complete |
Deerpark Middle School | Repurpose classroom wing to 4 learning centers | $38,400 | 4 | Complete |
Grisham Middle School | Plumbing projects | $68,750 | 4 | Complete |
Grisham Middle School | Addition & remodel kitchen area | $210,120 | 2 | Complete |
Grisham Middle School | Interior renovations (marker boards, cabinets) | $325,000 | 2,4 | Complete |
Grisham Middle School | Install security/access systems | $100,000 | 3 | Complete |
Grisham Middle School | Install security cameras system | $180,000 | 2,3 | Complete |
Grisham Middle School | Replace VCT in cafeteria | $81,000 | 4 | Complete |
Grisham Middle School | Replace fire alarm system | $101,250 | 4 | Complete |
Grisham Middle School | HVAC replacement project | $434,200 | 1 | Complete |
Grisham Middle School | Replace roofing system | $130,000 | 4 | Complete |
Grisham Middle School | Interior renovations (classroom modifications) | $70,000 | 1 | Complete |
Grisham Middle School | Interior renovations (gym ceiling/lights) | $91,000 | 4 | Complete |
Ridgeview Middle School | Install security cameras | $192,000 | 2,3 | Complete |
Walsh Middle School | New Middle School at Walsh Ranch | $34,170,560 | 1,2 | Complete |
$42,288,776 |
CAMPUS | PROJECT | BUDGET | SALE | STATUS |
Cedar Ridge High School | New High School at Gattis School Road | $83,988,178 | 1,2,4 | Complete |
McNeil High School | HVAC projects (science rooms ventilation) | $65,000 | 3 | Complete |
McNeil High School | New fire alarm system | $540,000 | 1 | Complete |
McNeil High School | Replace PA, clock and bell systems | $418,500 | 1 | Complete |
McNeil High School | HVAC projects (insulation, VFD’s, HVAC units | $252,200 | 3,4 | Complete |
McNeil High School | Convert 8 Classrooms to 4 science labs | $975,000 | 2 | Complete |
McNeil High School | Artificial Turf Field Replacement | $1,150,000 | Complete | |
Round Rock High School | 100 building AHU’s & field house Lennox units | $1,440,000 | 2,3,4 | Complete |
Round Rock High School | HVAC Projects (outside air upgrade & VAV boxes) | $89,050 | 1,2 | Complete |
Round Rock High School | Replace chiller/boiler water piping above roof (CANCELLED) | $585,000 | 2 | Complete |
Round Rock High School | Reroof existing system (field house roof only) | $1,171,875 | 1,2 | Complete |
Round Rock High School | Site drainage renovations (concrete flume) | $96,000 | 3 | Complete |
Round Rock High School | Upgrade science lab exhaust ventilation | $82,500 | 2 | Complete |
Round Rock High School | Add more security cameras | $12,000 | 1 | Complete |
Round Rock High School | Remove and replace all carpet in the 300 wing | $79,255 | 1 | Complete |
Round Rock High School | Campus Master Plan | $50,000 | 1 | Complete |
Round Rock High School | Convert 10 science classrooms to 5 science | $1,218,750 | 2,3 | Complete |
Round Rock High School | Additions & renovations | $10,066,073 | 1,2 | Complete |
Round Rock Opportunity Center | Building additions (classrooms, restrooms) | $2,618,064 | 2 | Complete |
Round Rock Opportunity Center | Building additions (gym) | $873,792 | 2 | Complete |
Hernandez Middle School | Replace SEMCO unit at the office area | $468,000 | 4 | Complete |
Stony Point High School | 10 science classrooms/restroom | $5,726,172 | 2 | Complete |
Stony Point High School | Replace front entrance storefront doors | $52,000 | 3 | Complete |
Stony Point High School | Artificial Turf Field Replacement | Complete | ||
Westwood High School | Install security cameras & lights | $240,000 | 1 | Complete |
Westwood High School | Add lighting at back of school (part of security camera project) | Complete | ||
Westwood High School | Replace existing clock system | $65,000 | 4 | Complete |
Westwood High School | Replace existing fire alarm system | $438,750 | 4 | Complete |
Westwood High School | Replace and rekey all interior/exterior doors | $110,000 | 4 | Complete |
Westwood High School | Campus Master Plan | $50,000 | 1 | Complete |
Westwood High School | Additions & Renovations | $10,066,072 | 1,2 | Complete |
Westwood High School | Artificial Turf Field Replacement | Complete | ||
$121,837,231 |
CAMPUS | PROJECT | BUDGET | SALE | STATUS |
Central Administration | Replace existing fire alarm system | $81,000 | 4 | Complete |
Central Administration | Add HVAC to MIS and Finance areas | $175,500 | 1 | Complete |
Central Administration | Electrical upgrades (lighting & distribution) | $72,800 | 3,4 | Complete |
District-Wide | Emergency power for fiber optic super-ring sites | $102,000 | 1 | Complete |
District-Wide | Install 2″ air gap for floor sinks/hub drains | $144,000 | 1,2,4 |
Complete |
District-Wide | Replace wooden ramps with aluminum ramps | $660,000 | 1,2,4 | Complete |
District-Wide | Repairs to detention/water quality ponds | $183,000 | 1,2,4 | Complete |
District-Wide | Replace carpet/renovate toilets at portables | $720,000 | 1,3 | Complete |
District-Wide | Backflow/cross connection compliance (irrigation) | $416,000 | 1,2,4 | Complete |
District-Wide | Asbestos abatement-VCT flooring | $439,709 | 1,2,4 | Complete |
Food Service Department | Install security/access system (CK1) | $40,500 | 1 | Complete |
Food Service Department | Replace HVAC system, ductwork & exhaust fans | $254,800 | 1,2,3 | Complete |
Food Service Department | Replace the split system serving the bakery area | $80,600 | 1,2 | Complete |
Food Service Department | Replace existing baking unit | $144,000 | 3 | Complete |
Food Service Department | Install new exterior walk-in freezer | $156,000 | 1 | Complete |
Maintenance Department | Site renovations (fencing) | $39,600 | 3 | Complete |
New ES Site (West) | Future elementary school site | $1,505,000 | 4 | Complete |
New ES Site at Paloma Lake | Future elementary school site | $1,505,000 | 2 | Complete |
Transportation | (Eastside) Add additional parking area | $258,000 | 1 | Complete |
Transportation | (Westside) Electrical distribution | $24,000 | 1 | Complete |
Transportation | (Westside) Install fire sprinkler system | $78,000 | 3,4 | Complete |
Transportation | (Eastside) Install fire alarm and sprinkler system | $78,000 | 3,4 | Complete |
Transportation | (Westside) Site renovations (tire shed storage) | $30,000 | 1 | Complete |
Transportation | (Eastside) Add 12000 gallon UST for diesel | $60,000 | 1 | Complete |
$7,247,509 |
CAMPUS | PROJECT | BUDGET | PROP # |
Wells Branch Elementary | Technology 06-07 (Desktop PC Refresh) | $200,000 | 2 |
Anderson Mill Elementary | Technology 06-07 (Desktop Refresh) | $200,000 | 2 |
Bluebonnet Elementary | Technology 06-07 (Desktop Refresh) | $200,000 | 2 |
Brushy Creek Elementary | Technology 06-07 (Desktop Refresh) | $200,000 | 2 |
Caldwell Heights Elementary | Technology 06-07 (Desktop Refresh) | $200,000 | 2 |
Deep Wood Elementary | Technology 06-07 (Desktop Refresh) | $200,000 | 2 |
Double File Trail Elementary | Technology 06-07 (Desktop Refresh) | $200,000 | 2 |
Fern Bluff Elementary | Technology 06-07 (Desktop Refresh) | $200,000 | 2 |
Gattis Elementary | Technology 06-07 (Desktop Refresh) | $200,000 | 2 |
Jollyville Elementary | Technology 06-07 (Desktop Refresh) | $200,000 | 2 |
Live Oak Elementary | Technology 06-07 (Desktop Refresh) | $200,000 | 2 |
Old Town Elementary | Technology 06-07 (Desktop Refresh) | $200,000 | 2 |
Purple Sage Elementary | Technology 06-07 (Desktop Refresh) | $200,000 | 2 |
Robertson Elementary | Technology 06-07 (Desktop Refresh) | $200,000 | 2 |
Spicewood Elementary | Technology 06-07 (Desktop Refresh) | $200,000 | 2 |
Stony Point High School | Technology 06-07 (Desktop Refresh) | $750,000 | 2 |
Voigt Elementary | Technology 06-07 (Desktop Refresh) | $200,000 | 2 |
McNeil High School | Technology 06-07 (I C Project) | $400,000 | 4 |
Round Rock High School | Technology 06-07 (I C Project) | $400,000 | 4 |
Stony Point High School | Technology 06-07 (I C Project) | $400,000 | 4 |
Westwood High School | Technology 06-07 (I C Project) | $400,000 | 4 |
Grisham Middle School | Technology 06-07 (Laptop Refresh) | $57,600 | 2 |
Round Rock Opportunity Center | Technology 06-07 (Laptop Refresh) | $28,800 | 2 |
Success (East) | Technology 06-07 (Laptop Refresh) | $14,400 | 2 |
C.D. Fulkes Middle School | Technology 06-07 (Notebook Refresh) | $57,600 | 2 |
Chisholm Trail Middle School | Technology 06-07 (Notebook Refresh) | $57,600 | 2 |
Deerpark Middle School | Technology 06-07 (Notebook Refresh) | $57,600 | 2 |
Hopewell Middle School | Technology 06-07 (Notebook Refresh) | $259,200 | 2 |
Ridgeview Middle School | Technology 06-07 (Notebook Refresh) | $86,400 | 2 |
Stony Point 9th Grade Campus | Technology 06-07 (Notebook Refresh) | $57,600 | 2 |
Success (West) | Technology 06-07 (Notebook Refresh) | $14,400 | 2 |
Union Hill Elementary | Technology 06-07 (Notebook Refresh) | $172,800 | 2 |
McNeil High School | Technology 06-07 (Wireless Project) | $180,000 | 2 |
Round Rock High School | Technology 06-07 (Wireless Project) | $180,000 | 2 |
Stony Point High School | Technology 06-07 (Wireless Project) | $180,000 | 2 |
Westwood High School | Technology 06-07 (Wireless Project) | $180,000 | 2 |
$7,134,000 |
CAMPUS | PROJECT | BUDGET | PROP # |
Construction Department | Career Technology Equipment | $185,130 | 2 |
Construction Department | Music equipment for all High Schools | $192,389 | 2 |
Deerpark Middle School | Upgrade Equip & Tech | $50,000 | 2 |
Transportation | Install digital cameras on buses 06-07 | $44,800 | 2 |
Transportation | Install digital cameras on buses 07-08 | $44,800 | 2 |
Transportation | Purchase New Buses 06-07 | $1,350,000 | 1 |
$1,927,119 |